The Redemption Project Newsroom

The Redemption Project Newsroom

An $11.3 Billion Energy Campus Has No Customer Yet. Cleveland Is Being Asked to Zone the Possibility.

The Redemption Project's avatar
Newsroom TRP's avatar
Brandon Burley's avatar
The Redemption Project, Newsroom TRP, and Brandon Burley
Aug 31, 2026
∙ Paid

Project River would pair as much as 1,500 megawatts of onsite generation with a future data center or other industrial user. Developers have begun the annexation and zoning process, but the end user, power-plant operator, final permits, executed utility agreements and incentive terms remain unsettled.

By The Redemption Project Newsroom
East Tennessee / AI / Energy / Land Use / Follow the Dollar

CLEVELAND, Tenn. — The largest number attached to Project River is $11.3 billion. The more consequential number at this stage may be zero: The developers proposing an approximately 850-acre energy and industrial campus in Bradley County say they have no signed end user and no offtake agreement committing anyone to buy the enormous amount of electricity they hope to produce.

Project River says that plainly on its own website. Mitchell Simpson, CEO of the development company, similarly told WTVC that the group knows it is developing power generation but does not yet know what ultimately will consume the power. A hyperscale data center is one possibility; the developers say other energy-intensive industrial users also could occupy the campus.

That does not make Project River imaginary. Developers say they have begun the process of annexing and rezoning the property into Cleveland. TVA says it is conducting an interconnection study, and the development team has published a detailed four-phase concept for construction.

But it does mean local government is being asked to make consequential land-use decisions before the identity of the eventual customer, the final electrical load, the power-plant operator and several other major pieces of the project are settled.

That makes the zoning documents more important than the renderings

What Project River actually proposes

Project River envisions a campus west of Interstate 75 and north of Old Lower River Road that ultimately could generate as much as 1,500 megawatts onsite — 1,000 megawatts from natural gas and 500 megawatts from woody biomass.

The developer describes a four-phase build lasting roughly five years. Natural-gas generation would begin first at 250 megawatts, followed by additional gas generation and two 250-megawatt biomass increments. In the final phase, the project also proposes access to as much as 360 megawatts from TVA for backup and periods of peak demand.

That distinction matters. Project River sometimes describes the completed campus as having 1,860 megawatts of total power capacity, but only 1,500 megawatts would be generated onsite. The additional 360 megawatts would come from the regional grid.

Project River’s website calls that component a “TVA grid reservation.” TVA’s public description is more preliminary. Spokesman Scott Fiedler told the Chattanooga Times Free Press that TVA currently is conducting an interconnection study to determine the cost, scope and timeline of the project.

That confirms a live TVA review is underway. It does not yet tell the public what transmission or substation upgrades will be required, what they will cost, who will pay for them or whether the final arrangement will provide the full 360 megawatts on the terms Project River describes.

Those answers matter because Project River also promises residents that its operations will not raise their electric bills.

The mechanism proving that promise has not yet been made public.

The $11.3 billion is an estimate, not a committed investment

Developers estimate the campus could represent approximately $11.3 billion in private investment if fully built.

The Times Free Press reported that the current estimate includes $7.3 billion for data-center buildings, $1.5 billion for the natural-gas plant, $1.25 billion for the biomass plant, $750 million in transmission technology and $500 million for site work and other buildings. The estimate does not include servers and other information-technology hardware that a future data-center customer would install.

That also explains why a separate $7.3 billion number has appeared in discussion of the project: it represents the estimated data-center building component, not the entire campus.

The $11.3 billion still should be described as a developer estimate, not money already committed to Bradley County.

The same is true of the jobs.

Project River projects approximately 900 permanent onsite positions and 1,700 additional jobs in forestry, logging, trucking and related industries. The onsite figure includes 525 projected data-center positions, 250 jobs associated with power generation and 125 in biomass handling.

More than half of the claimed 2,600 ongoing jobs therefore are indirect, while more than half of the projected onsite jobs depend on the data-center component of a campus that does not yet have a data-center customer.

Those projections may ultimately materialize.

The land-use decision arrives before anyone knows whether they will.

Cleveland, not Bradley County, will make the next zoning decision

The local-government distinction may be the most important part of the current process.

Bradley County adopted specific data-center regulations in April. In unincorporated portions of the county, data centers are restricted to the I-2 Special Impact Industrial District and generally must remain at least 3,000 feet from residential zones, existing dwellings, churches, schools and other public gathering places. The county also imposes a 60-decibel property-line limit and requires written verification from the public electric utility that infrastructure is adequately sized to serve the proposed load.

Project River, however, is pursuing annexation into Cleveland.

That does not establish that annexation is intended to avoid Bradley County’s restrictions. Developers have said annexation is necessary to obtain city services, and annexation is a normal development tool.

It does mean a different zoning code would govern the property.

Cleveland’s current zoning ordinance does not contain a separately named “data center” use. Project River developers have said they expect to pursue the property as a Planned Unit Development, or PUD.

That gives the city substantial power over what comes next.

Cleveland can turn promises into enforceable conditions

A PUD is not simply a broad zoning label.

Cleveland’s ordinance says City Council retains authority to impose limitations and regulations protecting public health, safety and welfare. During conceptual review, the Planning Commission may require performance standards involving noise, lighting, odors, truck traffic, hours of operation, outdoor storage, setbacks and buffering.

The final PUD Development Plan goes further.

Under Cleveland’s ordinance, it becomes a recorded legal instrument adopted by City Council and binding on the property owners, developers, heirs and assigns. It may specify permitted uses, buffers, setbacks, noise and operating standards, monitoring and reporting, project phasing, required public improvements and an expiration date. It also must acknowledge the developer’s obligation to obtain applicable federal, state and local permits.

Significant future changes can require amendment of the PUD and another Planning Commission and City Council process.

That matters enormously for a project without a customer.

The company that ultimately occupies Project River may not be the company presenting the concept today. The power operator could change. The property could be sold. Technology could change during a five-year buildout.

If Cleveland wants Project River’s promises to survive those changes, the city does not have to rely on a website remaining online.

The website contains promises; the PUD can contain remedies.

“Zero daily municipal water” still needs a complete water balance

Water is among Project River’s broadest commitments.

The developer says the plant would capture moisture while drying biomass, treat it and recirculate it through a closed-loop cooling system. Project River says the system would replace only about 0.1% of the loop during normal operation and would require no day-to-day municipal water. It also says the process could produce excess water.

Those are unusually specific claims.

They still leave important engineering questions unanswered.

How much water is required to fill the system initially? What supplies the campus before biomass operations begin? How much firewater is required for a campus containing large gas and biomass generation facilities? What happens during maintenance, extreme heat, drought or an outage? How much potable water will employees use? What happens to recovered water that cannot be reused?

The project website also says that any regulated water handling is permitted and monitored under “the project’s NPDES permit.”

TRP did not locate a Project River-specific NPDES permit in the public TDEC materials reviewed for this article. That does not establish that no application or permit exists. It means the permit number and status should be produced so the public can examine what it actually authorizes.

At minimum, construction on an 850-acre development will involve substantial stormwater regulation. Tennessee generally requires construction-stormwater coverage when clearing, grading or excavation disturbs one acre or more. Water withdrawals reaching 10,000 gallons on any day also are subject to state registration requirements, while point-source pollutant discharges can require NPDES authorization.

The useful document is not another statement saying the campus uses zero water.

It is an annual water balance showing every input and output under normal and abnormal conditions.

The biomass number has to be reconciled

Project River’s forestry component creates another numerical question.

Its current website says the full biomass operation would consume approximately 6 million tons of forest timber and residuals per year from within a 200-mile radius.

Developers told the Times Free Press 5 million tons annually.

A 1-million-ton difference is too large to dismiss as rounding. It is approximately 2,740 tons per day averaged across a year.

The project also needs to say whether those figures are wet tons or dry tons, what moisture content is assumed and how much material would arrive by truck, rail or another transportation mode.

The traffic implications could be substantial. If 6 million tons arrived entirely by road every day of the year in 25-ton loads, the arithmetic would produce about 658 loaded trucks per day. At 30 tons per load, it would be about 548.

Those figures are scenarios, not Project River traffic forecasts. The developer has not disclosed the final mode split, operating days, truck payload, haul routes, rail use or backhauls.

That is precisely why the project needs a traffic-impact analysis before the relevant land-use conditions are finalized.

The forestry claim requires similar scrutiny. Project River says it intends primarily to consume lower-grade timber and residual material and describes the biomass operation as carbon-negative. The company says its verified carbon methodology and tonnage figures will be published later.

Until that lifecycle analysis is available, “carbon-negative” remains the developer’s conclusion rather than an independently established project fact.

The power plants will create a separate regulatory record

A local PUD cannot substitute for state environmental permitting.

Tennessee generally requires an air construction permit before a nonexempt air-contaminant source is built. Facilities with sufficiently large potential emissions can fall under the Title V program, which carries additional permitting, monitoring and reporting requirements.

A proposed 1,000-megawatt natural-gas plant and 500-megawatt biomass operation therefore should eventually generate a detailed regulatory record showing the generating equipment, expected operating hours, fuel consumption, emissions, controls, modeling and monitoring requirements.

Natural-gas supply presents another infrastructure question.

Enbridge says its East Tennessee Natural Gas system extends 1,526 miles and has systemwide peak-day capacity of about 1.86 billion cubic feet per day. That does not establish that enough firm capacity is available at the Bradley County location to serve Project River.

The relevant records are the project’s expected daily gas demand, any firm transportation commitment, necessary lateral or compression work and who would finance those additions.

The same principle applies to TVA.

A study is evidence that the process is moving.

It is not the same thing as a completed agreement.

Follow the public support as well as the private investment

Project River describes the $11.3 billion as private investment.

That does not answer whether the ultimate project or its tenant will receive public tax benefits or infrastructure support.

Tennessee already offers a statutory tax program for qualifying data centers. Current Revenue Department materials say a qualifying facility generally must make more than $100 million in capital investment and create at least 15 qualifying new full-time jobs. Eligible data centers can receive sales-tax exemptions on specified computing, backup-power and cooling equipment and a 1.5% state sales-tax rate on electricity.

Project River has no identified data-center tenant, so there is no basis yet to say a future customer has qualified for those benefits.

Local incentives are another question.

Cities, counties and industrial development boards can use tools such as payment-in-lieu-of-tax agreements and other development incentives. Nothing in the public record reviewed for this article establishes that Project River has received a PILOT, TIF or other local incentive package.

Before Cleveland reaches final approval, the public should be able to see any requested tax treatment alongside the developer’s estimate of new tax revenue.

The relevant number is not merely gross investment.

It is the net public benefit after incentives and public costs are included.

The public meetings are the beginning, not the approval

Project River’s developers are holding community meetings from 6 to 8 p.m. Sept. 1 and 10 a.m. to noon Sept. 12 at the PIE Innovation Center, 2337 Parker St. NE in Cleveland. Those are developer-hosted meetings intended to present the project and receive public questions. They are not substitutes for formal Planning Commission and City Council hearings.

As of Friday morning, Cleveland’s online Agenda Center showed the Aug. 18 Planning Commission meeting as the most recent posted Planning Commission agenda. The public packet for Project River’s next formal land-use step had not yet appeared there.

When it does, that packet may be more important than any promotional rendering released so far.

It should show exactly what land is being annexed, what uses the PUD permits, what conditions accompany those uses and what happens if the eventual customer wants something materially different.

Project River could become one of the largest private investments in Tennessee history. It could rebuild part of a regional forestry economy, create high-paying jobs and provide a model for serving enormous industrial electric loads without putting the primary demand on TVA’s grid.

Those possibilities deserve serious consideration.

So do the unresolved questions.

Cleveland is not being asked to approve a finished data center with a known operator, fixed load and complete set of permits. It is being asked to establish what may eventually be built on hundreds of acres while the customer and some of the most consequential engineering and financial details remain unsettled.

That makes the government document more important than the rendering.

The question is not whether Cleveland should believe Project River’s promises. It is which promises Cleveland will require the project — and whoever eventually owns it — to keep.


Behind the Reporting: What the Website Says — and What the Government Documents Can Actually Prove

Paid subscribers get the evidence ledger, numerical checks, document library and records strategy behind this report.

Project River has published considerably more detail than many large industrial projects do at this stage. That is useful because it gives the public specific claims that eventually can be tested against applications, permits and contracts.

It also created several discrepancies during our document review.

User's avatar

Continue reading this post for free, courtesy of The Redemption Project.

Or purchase a paid subscription.
Newsroom TRP's avatar
A guest post by
Newsroom TRP
The Newsroom for The Redemption Project
Subscribe to Newsroom
Brandon Burley's avatar
A guest post by
Brandon Burley
Your home for Christ centered public policy, criminal justice, explaination, and conversation.
Subscribe to Brandon
© 2026 Brandon L. Burley / The Redemption Project · Privacy ∙ Terms ∙ Collection notice
Start your SubstackGet the app
Substack is the home for great culture